This item was deferred from the April 26 meeting.
Duke Energy Carolinas has requested that the board grant a right-of-way affecting a 20-foot strip to permit the construction or modifications of facilities presently proposed at 2225 S. Holden Road, Greensboro, North Carolina for the purpose of extending three phase underground primary installation to the new transformer location.
The requested right-of-way would have a width of 10 feet on each side of a centerline determined by the centerline of the electrical facilities as installed, to construct, maintain and operate underground lines and conduits with other apparatus and appliances, either above ground or below ground, to include transformers and service connectors, for the purpose of transporting electricity.
Further, this right-of-way would permit the construction or modifications of facilities presently proposed. This would also include the rights to inspect and maintain these same lines as needed.
RECOMMENDATION: The administration recommends that the board approve the right-of-way requested by Duke Energy Carolinas, as described herein, affecting The Academy at Smith property.
Attachment #1 - Agreement
Attachment #2 - Site Map
|