Project Update: Kiser Middle School

  • scheduleLatest Project Update (August 2023)

    Current phase: Construction

    Expected completion: June 2024

    Key Points of Interest

    • Footings are nearly complete
    • Underground plumbing work is 60% complete
    • Masonry due on site in late August

Key Project Information

  •  Bid Phase

    BudgetEstimated budget: $55,478,632  

    Space AllocationsAction: Rebuild on the Grimsley/Kiser campus

    TimelineTimeline for project

    • Phase: 2
    • Begin date: To be determined
    • Estimated completion date: June 2024

    Bid for Suppliers TimelineBid for bond suppliers timeline: 2022

    Age of the buildingYear built: 1957

Questions or Feedback?

Address & Map

Last Modified on August 28, 2023