Project Update: Foust Gaming & Robotics School

  • Latest Project Update (January 2024)

    Current phase: Construction

    onschedule

    Expected completion: 2024

    The Foust Robotics and Gaming Magnet School is the first of its kind in Guilford County, and one of the first gaming and robotics elementary schools in the country.  

    Key Points of Interest

    • U/G utilities nearing completion.
    • In wall electrical rough-in everywhere.
    • Masonry walls toward roof line everywhere A2 - B3.
    • 2nd floor masonry is underway at A1.
    • Door frames being installed everywhere.
    • Exterior load bearing walls in A1 are underway.
    • Site work continues.
    • Continuing waterproofing exterior brick.
    • MEP underway in all areas.
    • Site sanitary sewer is underway.
    • B2 roof membrane is being installed.
    • B1 Overhead Sprinkler is underway.
    • Brick Veneer / Architectural Block underway everywhere.

Key Project Information

  •  Construction Phase Image

    BudgetEstimated budget: $31,333,469  


    Space AllocationsAction: Rebuild on site

     

    TimelineTimeline for project

    • Phase: 2
    • Begin date: To be determined
    • Estimated completion date: August 2024

    Bid for Suppliers TimelineBid for bond suppliers timeline: 2022

    Age of the buildingYear built: 1965

Questions or Feedback?

Address & Map

Last Modified on January 19, 2024